Vopak Terminal, Port Botany
Vopak Terminal, Port Botany
Port Botany was an engaging, technical and precise project, Endacom used all their experience to deliver a product meeting up to the clients’ expectations. Every Structure of reinforcement works was engineered so it was chemical resilient and containing meeting the EPA Standards .
Endacom were engaged to complete all Reinforcement works on this project including 200m chemical retaining wall and 900m of foundation ring beam for sheet pile, two blast walls and pump station, all pipe support and containment bunds , two massive pits to facilitate the excavation of and install of underground fuel delivery lines from the existing diesel storage to the new , all works had to be completed while keeping the whilst keeping the port Botany Road active.
Precision threaded bolts were sett throughout the project on top the bund containing walls to house six 10-meter light towers and across all pipe support plints to house every prefabbed pipe supports.
Endacom delivered on time and on budget for another successful project.
Key Points
900m of re-enforced chemical proof blast wall works
construction of 6m and nine meter chemical separation pit below sea level
All concrete support works for new diesel pipe install
All Storage facility concreting works